There are many examples of applications of blown fibre in private networks.
This example is for a UK-based oil refinery that has been utilising blown fibre since 1994/5, so
the site was one of the first to see the benefits of the technology.
Over the intervening years the network gradually expanded to provide a communication backbone
ring from the main data centre around the main refinery with a leg to the shipping berths for the
tankers bringing crude oil from around the world to be turned into petrol, diesel, LPG, paraffin
and a host of other products.
“What has really made a big difference to us,” explains the plant’s Infrastructure Engineer, “
is that we now have complete control of the activity so we can react very quickly to urgent needs.
With the Prysmian Sirocco solution, we have been able to buy equipment so that we can install the
fibres ourselves. Previously the refinery employed an installation company based many miles away.
Due to the distance involved, any delay to repair would be significant, with downtime at the site
potentially costing upwards of 0.5m per day. With this in mind we arranged for Prysmian to send
their trainer to the refinery and members of the team can now blow in a new fibre link in less time
than it would have taken a contractor to get to the site.”
They also appreciate the flexibility that Sirocco provides. Initial links were provided
with multiples of 4 fibre 62.5/125 multimode. With the introduction of the Sirocco 12 fibre, some
old fibres have been blown out and replaced with a 12 fibre 50/125 multimode unit releasing tubes
for later use. The change in preference for 50/125 was prompted by better performance and cheaper
active equipment. The maximum length installed so far in the network was an 880 metre connection to
the tanker berths although 1500 metre blows are planned. A 6km link is also planned, using
singlemode fibres to a duplicate server farm and further extensions to new buildings as services
become located outside the ‘blast zone’ – safety and security are an obvious priority to the
company.
One of the most challenging tasks for the infrastructure team is to provide the facilities
required during the refinery shutdown which occurs every four years. Communication services need to
be supplied to cabins located around the site, with an additional 180 telephones and 290 PCs being
required over a 6 week period. It takes 2 weeks just to allow for the refinery cooling process, but
when you start with operating temperatures at around 650°C, it’s not surprising. Traditionally,
robust, pre-terminated tight-buffered cables would be temporarily placed around the site, often
simply laid across the floor and then cut out after use. With a ducted blown fibre tube network in
place around the site, Sirocco fibre units can be blown in ready for the influx of contractors and
then blown out again when they’ve gone. “When working with an operation like this, the last thing
you want is concern about the reliability and efficiency of the communications network.” reflects
the Infrastructure Engineer.
• Managed flexibility – address normal and urgent demands
• Internal, trained staff and purchased equipment provide self-sufficiency
• Time-to-Repair in hours not days
• Temporary capacity demand surges can be flexibly accommodated
• Avoid unnecessary costs
But this is true throughout the year, not just at shutdown time. The blown fibre system is
used to provide site security and cameras, data communication, monitoring and metering using
hand-held units and will be extended to cover voice using IP telephones. “The Sirocco system has
also helped us in managing our budgets and the timeframes we can work under.” For example, some of
the contractors used would have a day’s journey to the plant, overnight accommodation and a day’s
journey back afterwards. And, because these companies have other customers, the work would
typically have to be scheduled 4-6 weeks ahead. With Sirocco, planning times can be shortened and
costs can be much lower. There are typically a dozen blown fibre projects on the go at one time to
extend, develop, introduce advanced controls and improve the current network. The Sirocco tubing is
primarily Direct Install, located inside a 100mm duct which provides the required crush protection
and ‘separation’ from any contamination by hydrocarbons. For example, in the lin to the berths,
19-way tube is used and then dropping off to 7 tubes. With a wide range of tube and fibre unit
options, they are able to develop their network to suit their current requirements, knowing that
their future needs will not be impaired. Even the choice of a 100mm duct leaves them space to add
further tubes when and if necessary. As some of the tubes may be in place for months or years
before being fibred, the Sirocco Tube Integrity & Length Tester (STILT) is invaluable to check
the route before blowing fibre. “Sirocco has made a big difference to the way we can manage our
network and respond to normal requirements and urgent changes,” concludes the Infrastructure
Engineer, “the key benefit for us is managed flexibility.”