Background Image
Table of Contents Table of Contents
Previous Page  95 348 Next Page
Information
Show Menu
Previous Page 95 348 Next Page
Page Background

95

OPERATIONAL RISKS

Responsibility for product quality/defects

Any defects in the design and manufacture of the Prysmian

Group's products could give rise to civil or criminal liability

in relation to customers or third parties. Therefore, the

Group, like other companies in the industry, is exposed to

the risk of legal action for product liability in the countries

where it operates. In line with the practice followed by many

industry operators, the Group has taken out insurance which

it considers provides adequate protection against the risks

arising from such liability. However, should such insurance

coverage be insufficient, the Group's results of operations

and financial condition could be adversely affected.

In addition, the Group's involvement in this kind of legal

action and any resulting liability could expose it to a damage

in reputation, with potential additional adverse consequenc-

es for its results of operations and financial condition.

Risks associated with non-compliance with the

contractual terms of turnkey projects

Projects relating to submarine or underground connections

with high/medium voltage cables feature contractual forms

that entail "turnkey" project management and so require

compliance with deadlines and quality standards, guaran-

teed by penalties calculated as an agreed percentage of the

contract value and even involving the possibility of contract

termination.

The application of such penalties, the obligation to compen-

sate any damages as well as indirect effects on the supply

chain in the event of late delivery or production problems,

could significantly affect project performance and hence

the Group's margins (for example, the Western HVDC Link

project). Possible damage to market reputation cannot be

ruled out.

Given the complexity of "turnkey" projects, Prysmian has

implemented a quality management process involving

extensive testing of cables and accessories before delivery

and installation, as well as specific ad hoc insurance coverage,

often through a pool of insurers, able to mitigate exposure to

risks arising from production through to delivery.

Moreover, the ERM findings for this particular risk have led

the Risk Management department, with the support of the

Commercial area, to implement a systematic process of

risk assessment for "turnkey" projects from as early as the

bidding stage, with the aim of identifying, assessing and

monitoring over time the Group's exposure to specific risks

and of taking the necessary mitigation actions. The decision

to present a bid proposal to the customer therefore also

depends on the results of risk assessment.

In particular, during the last few days of April, the manu-

facture of the cables for the Western HVDC Link project in

the United Kingdom encountered some technical problems,

which were duly placed under technical investigation. As a

result, for the purposes of the Quarterly Financial Report

at 31 March 2014, the Directors had felt unable to estimate

reliably the outcome of this contract, and so its revenues

were recognised to the extent of the costs incurred. Following

subsequent testing of the quality of the cable produced and

analysis of the materials and the manufacturing process,

the Directors felt able to make a reliable estimate of the

project's revenues and costs. This led to the full elimination

of the margins previously recognised on the contract and

the recognition of a provision to cover the expected contract

loss, with a total impact of Euro 53 million. In addition,

the technical problems described above have resulted in

the non-recognition of Euro 41 million in margins originally

expected in 2014. Consequently, including non-recognition

of the margin originally expected on this project in the year,

the overall negative impact of the Western HVDC Link (UK)

project on the results for 2014 was Euro 94 million.

It is not possible to exclude that in the future, in the face

of any further technical problems on the Western HVDC

Link contract, the Group may incur additional losses on top

of those estimated by the Directors in the current Annual

Financial Report.

Risk of business interruption through dependence

on key assets

The submarine cables business is heavily dependent on

certain key assets, such as the Arco Felice plant in Italy for the

production of a particular type of cable and the cable-laying

ships, the "Giulio Verne" and the "Cable Enterprise", some of

whose technical capabilities are hard to find on the market.